Home Eco News Eco News / Issue 74 June 2010 BP oil spill uncertainty as 'Top Kill' method fails: Live Images Feed
BP oil spill uncertainty as 'Top Kill' method fails: Live Images Feed

BP

oil-spillPreparations are now underway for the deployment of the lower marine riser package (LMRP) cap containment system. Remotely operated vehicles (ROVs) are engaged in preliminary operations, including preparing for operations to cut through and separate the damaged riser from the LMRP at the top of the Deepwater Horizon's failed blow-out preventer (BOP).

A Live Feed of images from the spill provided by ROV's is available here.

Deployment of the system will involve connecting the containment cap to a riser from the Discoverer Enterprise drillship and then placing it over the LMRP, with the intention of capturing most of the oil and gas flowing from the well and transporting it to the drillship on the surface.

All of these operations, including the cutting of the riser, are complex, involve risks and uncertainties, and have to be carried out by ROVs at 5,000 feet under water. Systems such as the LMRP containment cap have never before been deployed at these depths and conditions, and their efficiency and ability to contain the oil and gas cannot be assured. It is currently anticipated that attachment of the LMRP cap will be attempted later this week; however, operational delays could impact anticipated timeframes.

Preparations to use the Discoverer Enterprise to deploy the LMRP cap and the intended severing of the damaged riser mean that the riser insertion tube tool, previously deployed, will not be reinserted into the main leak at the end of the riser.

Work on the first relief well, which started on May 2, continues and it has currently reached a depth of 12,090 feet. Work on the second relief well, which started on May 16, had reached a depth of 8,576 feet before drilling was temporarily suspended on May 26. Drilling operations on the second relief well resumed on May 30. Both wells are still estimated to take around three months to complete from commencement of drilling.

Surface Spill Response and Containment
Work continues to collect and disperse oil that has reached the surface of the sea, to protect the shoreline of the Gulf of Mexico, and to collect and clean up any oil that has reached shore.

Over 1,600 vessels are now involved in the response effort, including skimmers, tugs, barges and recovery vessels. Operations to skim oil from the surface of the water have now recovered, in total, some 321,000 barrels (13.5 million gallons) of oily liquid.

The total length of containment boom deployed as part of efforts to prevent oil reaching the coast is now over 1.9 million feet, and an additional 1.8 million feet of sorbent boom has also been deployed.

So far approximately 30,000 claims have been submitted and more than 15,000 payments already have been made, totalling some $40 million. BP has received more than 110,000 calls into its help lines to date.

BP started the "top kill" operations to stop the flow of oil from the MC252 well in the Gulf of Mexico at 1300 CDT on May 26, 2010.

The procedure was intended to stem the flow of oil and gas and ultimately kill the well by injecting heavy drilling fluids through the blow-out preventer on the seabed, down into the well.

Despite successfully pumping a total of over 30,000 barrels of heavy mud, in three attempts at rates of up to 80 barrels a minute, and deploying a wide range of different bridging materials, the operation did not overcome the flow from the well.

The US Government, together with BP, have decided to move to the next step in the subsea operations, the deployment of the Lower Marine Riser Package (LMRP) Cap Containment System.

The operational plan first involves cutting and then removing the damaged riser from the top of the failed Blow-Out Preventer (BOP) to leave a cleanly-cut pipe at the top of the BOP's LMRP. The cap is designed to be connected to a riser from the Discoverer Enterprise drillship and placed over the LMRP with the intention of capturing most of the oil and gas flowing from the well. The LMRP cap is already on site and it is currently anticipated that it will be connected in about four days.

This operation has not been previously carried out in 5,000 feet of water and the successful deployment of the containment system cannot be assured.

Drilling of the first relief well continues and is currently at 12,090 feet. Drilling of the second relief well is temporarily suspended and is expected to recommence shortly from 8,576 feet.

The cost of the response to date amounts to about $990 million, including the cost of the spill response, containment, relief well drilling, grants to the Gulf states, claims paid and federal costs. It is too early to quantify other potential costs and liabilities associated with the incident.

Share
 
facebook twitter feed vimeo